T400 Controller Facilities Manual
667/EB/20200/000 Page 14-5 Issue 9
HONG KONG: Startup sequence:
A 7-10 second blackout, followed by all red usually 8 seconds.
Then phases in starting stage go immediately to green.
The LRT phase sequence is:
Stop - Proceed - Flashing Proceed - Stop.
Proceed may be ahead, and/or left turn and/or right turn
proceed signals. If two different ahead moves are required, a
separate phase is required for each.
The vehicle phase sequence will be:
red - red/amber - green - amber - red.
The pedestrian phase sequence will be:
red man - green man - flashing green man - red man
Supply: 200V 50Hz
SYRIA: Flashing amber start-up and part-time.
Traffic: red - green - amber - red.
Ped: standard (with three second blackout).
Supply: 240V 50Hz (Damascus).
SRI LANKA: As Bahrain, but with flashing amber start-up. 240V 50Hz.
TRINIDAD: Flashing amber start-up with flashing amber (main road) and
flashing red (side road) part-time.
Traffic: red - green - amber - red.
Ped: standard sequence.
Both 240V 50Hz and 110V 60Hz are used in Trinidad and
Tobago depending on the actual location.
ZAMBIA: As Syria with 240V 50Hz.