T400 Controller Facilities Manual
667/EB/20200/000 Page 9-43 Issue 9
9.9.1 Example Of Simple Linked Installation
A simple linked installation covering three intersections on a main road into a city
(Figure 9.6) is used as an example. At each of the three intersections A, B and C, a
cableless linking facility is used to drive the respective controllers.
A 3-intersection stretch of main road, indicating group timings at each intersection and
progressive plan starts/offsets along the route, for:
(a) Morning into-city peak (Plan 0)
(b) Evening out-of-city peak (Plan 1)
Figure 9.6 - SIMPLE LINKED INSTALLATION
(a) Morning Peak (Plan 0)
A 20 Secs15 Secs
08:30:0008:30:35 08:30:20Plan Start:
CB
CITY
CENTRE
30 Secs
15 Secs
Controller Timings:
20 Secs
25 Secs
20 Secs
25 Secs
(b) Evening Peak (Plan 1)
A 27 Secs19 Secs
16:15:4616:15:00 16:15:19Plan Start:
CB
CITY
CENTRE
20 Secs
40 Secs
15 Secs
45 Secs
25 Secs
35 Secs
Controller Timings:
9.9.2 Offset Timing
During morning peaks, traffic flowing into the city centre (C-B-A) is required to meet
a succession of signals at green (a ‘green wave’). Typically, free flowing morning peak
traffic takes 20 seconds to travel from C to B and 15 seconds from B to A. The main
road lights at B should therefore change to green 20 seconds after those at C, and
those at A a further 15 seconds later. Offset timings of 20 seconds at B with respect to
C, and 15 seconds at A with respect to B are therefore required.