Commissioning and optimization (software)
7.5 Commissioning of the fail-safe functions
ET 200pro FC
Operating Instructions, 11/2007, A5E01100763B AA
117
When a password is entered (5 digits without leading zeros), it is compared to the password
stored in r9760.
If it is correct, i.e., if the two passwords match, access is granted.
If the password is incorrect, the parameters for fail-safe functions are disabled and the user
has to exit the commissioning mode for fail-safe functions manually using parameter
P3900 = 11. Parameter P3900 = 11 clears all previous changes that have been made to the
parameters for fail-safe functions.
Checksums
All parameters for fail-safe functions are verified with the aid of checksums, which guarantee
the integrity of the data stored in the drive processor's memory.
There are four checksums, two for each processor:
r9798 - Current checksum for P1
P9799 - Reference checksum for P1
r9898 - Current checksum for P2
P9899 - Reference checksum for P2
7.5.1 General information on acceptance tests
Description
In order to check the safety function parameters, an acceptance test must be carried out
after commissioning, after a reset and also whenever changes are made to a fail-safe
parameter data set associated with safety functions (e.g., via MMC). The acceptance test
must be logged and documented using appropriate means. This section contains an
example of a duly completed acceptance report. Acceptance reports must be archived using
appropriate means.
Acceptance test
An acceptance test must be carried out by the machine manufacturer in respect of any
safety functions that are enabled on the system.
Authorized person, acceptance certificate
Each of the safety functions must be checked by the relevant authorized personnel. Each
check must be documented/logged in an acceptance report and then signed off. The
acceptance report must be enclosed with or attached to the system's log book.
In this context, the term "authorized personnel" refers to any member of the machine
manufacturer's personnel with the requisite training and knowledge to carry out a safety
function acceptance test correctly.