Maxum II Initial Startup Procedures, Continued
Check for Proper Reporting of Results
In the main System Manager screen, double click in the analyzer icon at the bottom of the screen
to bring up the database tables. The analyzer name and IP address are located next to the
analyzer icon.
Press the “+“ next to the appropriate application, i.e., App 1, App 2, etc., to expand the list of
tables.
Double click on Tables to open an additional list of tables.
Double click on Result to open the result table. Verify the proper peak concentrations are
reported to the result table.