Utility Gas Supply Installation, Continued
Figure 2-4. Automatically Switched Carrier Gas Cylinders
Calibration Standard Supply Installation
The Calibration Standard Supply required is specified in the "Notes" block on the Block Diagram Utility
Connections sheet contained in the Application Drawing Package.
Mounting
Always mount the calibration standard cylinder as close to the analyzer as practical. When installing
calibration standard cylinders, always use new, clean, ¼” (.635 cm) stainless steel tubing and fittings for
the line between the cylinder and the analyzer. Before connecting the line to the cylinder, blow it out with
a clean, dry, inert gas and cap the open end of the tubing.
A certified calibration standard may be purchased from Siemens or another supplier. If Siemens supplies
the calibration standard, it will be noted in the "Notes" block on the Block Diagram Utility Connections
sheet contained in the Application Drawing Package.
Heat Tracing
Some vapor standards must be heated to prevent condensation. If heat tracing is required, it will be noted
in the "Notes" block on the Block Diagram Utility Connections sheet contained in the Application Drawing
Package.
When heat tracing is used, it is essential that none of the tubing be exposed to ambient conditions. Steam
tracing must be continuously sloped downward for draining any condensate, and it must have condensate
traps at any low points.
24