NoteThe correspondence between the device of EV5000 and the s7-300 software, as follows:
4X-DINV------------PID
e.g.4X-DINV1------------PID256 4X-DINV3------------PID260
3X-DINV------------PQD
e.g.3X-DINV1------------PQD256 3X-DINV3------------PQD260
4X -------------------PIW
e.g.4X1 --------------------PIW256 4X2--------------------PIW258
3X--------------------PQW
e.g.3X1---------------------PQW256 3X2---------------------PQW258
0X--------------------I
e.g.0X1--------------------I0.0 0X9--------------------I1.0
1X--------------------Q
e.g.1X1--------------------Q0.0 1X9--------------------Q1.0
4X_BIT -------------------PIWbinary
e.g.4X_BIT1.0~~1.15-------------------PIW256binary
3X_BIT--------------------PQWbinary
e.g. 3X_BIT1.0~~1.15--------------------PQW256binary
PLC software setting
Setup the GSD in the S7-300 software
Procedure
1.Close all stations in “HW Config”.
2.And select “option”-->”setup GSD”.
3. In the “installation *.GSD file” dialog box, select Source: folders contain *. GSD file, or
the STEP 7 project contain *. GSD file
4.Select one or more files from *.GSD file list, and then click on "install" button.
Copy the icon (. BMP file) to the relevant path, such as BRIDGE productBitmap_Device
= "EVIEW", that copy the "EVIEW" BMP file to the relevant path: c:\siemens\step7\s7data\nsbmp
or c:\siemens\cpbv51\bitmaps
After installation, you can find the appropriate symbol in "PROFIBUS DP\GATWAY".
Project configuration
1Use the guide to set up projects in the s7-300 software.
2Double click “DP” of "HW Config"->attribute->new