5-1
5. Installation
5.1 Machine Installation
1) Clean up the space necessary for
machine installation.
2) Make sure once again that the space
for machine installation is enough.
The space required is necessary to
fit as described in chapter 3.1.
3) According to the drawing's
indication as chapter 3.1, put the
machine on the foundation, and put
the foundation block on the marked
position.
4) According to the steps of chapter
4.5, and follow the opposite
sequence to disassemble the fix
bracket.
5) Take away the humidity absorbing
bags in the spindle zone and inside
cabinet.
6) Clean up two axis moving chip
guard.
7) Fill in clean lubrication oil into oil
tank till the oil is filled to middle
level line.
8) Fill new and clean hydraulic oil till
its upper line.
Note1.Refer to the sticker of oil
recommendation list on the machine
and fill in the necessary oil.
2.If machine is installed with angle bolt,
please contact Leadwell in advance
for further foundation drawing.