Installation
4.4 Communication
58
4.4.1 Profibus
If you have a system in master-slave combination, you must route the Profibus cable between the
inverters.
The Profibus cable (violet) must begin with the S7 CPU and end with an ET200. Both ends of the
Profibus connection must be terminated with the end switch in the Profibus connector.
The shield of the Profibus cable must be grounded on all housings.
ET 200 CUd with ADB
Figure 4-18 Profibus connection
Figure 4-19 Profibus cable routing for a master/slave combination