Post-Installation Test UMSITRPDS3-1
November 2010
5-12
11. Check and correct zero (4 mA) if necessary at zero bar.
12. Close the compensation valve (2).
13. Open the active pressure valves (3A and 3B) fully.
This completes the post-installation testing. Disconnect test equipment, connect any disconnected wires,
and restore any removed protective covers on the transmitter or other devices.
!